Hampton Beach Master Plan: Estimates of Proposed Costs

Return to Table of Contents

C. Estimates of Proposed Costs

The following estimate of costs refers to public costs associated with many of the recommendations contained in this Plan. The figures represent total project costs in 2001 dollars. Most costs were estimated based on given unit cost assumptions, to a concept level of detail. The costs may vary considerably depending on final design directions and technical issues encountered during design and construction. A detailed cost estimate is in Appendix IV.

 

Table 26. Proposed Cost Estimates for Major Improvement Projects at Hampton Beach

Recommendation

Costs

Phase I (0-2 years)

 

Streetscape/Sidewalk Improvements

$500,000

State Marina

$184,000

Total Phase I Costs

$684,000

   

Phase II (3-9 years)

 

New Hampton River Bridge

$9,625,000

State Park Area

$2,100,000

Ocean Boulevard Pavilions and Pedestrian Improvements

$847,000

New Performance Center

$1,500,000

Streetscape/Sidewalk Improvements

$7,407,000

Church/Highland Intersections

$2,062,000

Ashworth Avenue Reconstruction

$8,775,000

Open Space Improvements

$25,000

Sewer Improvements

$8,412,000

Flood Mitigation Projects

$3,000,000

Total Phase II Costs

$43,232,000

   

Phase III (10-50 years)

 

Ocean Boulevard Reconstruction

$4,200,000

Parking Structure

$4,000,000

Total Phase III Costs

$8,200,000

   

Total Projects Costs

$52,116,000

The Plan envisions an implementation period of 50 years. However, most of the projects within this plan are scheduled for the first ten years since they are needed to substantially improve the outdated transportation and facilities infrastructure such as intersections and parking as well as improve the image of Hampton Beach with projects such as sidewalk improvements.

 

Return to Table of Contents